Analysing Operational Performance: Unit Cost and Capacity - Worksheets, Questions and Revision
14 original exam-style questions - 3 pages of questions with a full mark scheme - free printable PDF.
Analysing Operational Performance: Unit Cost and Capacity revision guideWrite-in editionMore A Level Business practice
This topic is chapter 3 of A Level Business Topic Workbook 2.
2.8 Analysing Operational Performance: Unit Cost and Capacity
- A) Total revenue divided by number of workers
- B) Output per worker in a given time period
- C) Total costs divided by output
- D) The percentage of plant actually used
Period 1: actual output 24,000 loaves; number of production workers 60; total monthly production costs £36,000; maximum monthly capacity 30,000 loaves.
Period 2: actual output 27,000 loaves; number of production workers 60; total monthly production costs £37,800; maximum monthly capacity 30,000 loaves.
Using the Period 1 figures above, calculate Albion Baking Co's labour productivity in Period 1, in loaves per worker. Show your working.
Question 1
- B caoB1
- Answer: B
Question 2
- labour productivity = output / number of workers, or output per workerB1
- Answer: Labour productivity = output divided by number of workers (output per worker).
Question 3
- unit cost = total costs / output (average cost per unit)B1
- Answer: Unit cost = total costs divided by output (average cost per unit).
Question 4
- capacity utilisation = (actual output / maximum possible output) x 100%B1
- Answer: Capacity utilisation = (actual output divided by maximum possible output) x 100%.
Question 5
- 24,000 / 60 seenM1
- 400 loaves per worker caoA1
- Answer: 400 loaves per worker.
Question 6
- lower than expected demand for the product, causing fewer orders/salesB1
- temporary machine breakdowns or staff shortages reducing actual outputB1
- Answer: Any two, e.g. lower than expected demand; machine breakdowns or staff shortages reducing output.
Question 7
- 36,000 / 24,000 seenM1
- £1.50 per loaf caoA1
- Answer: £1.50 per loaf.
Question 8
- (24,000 / 30,000) x 100 seenM1
- 80% caoA1
- Answer: 80%.
Question 9
- (27,000 / 30,000) x 100 seenM1
- 90% caoA1
- Answer: 90%.
Question 10
- 27,000 / 60 seenM1
- 450 loaves per worker caoA1
- Answer: 450 loaves per worker.
Question 11
- 37,800 / 27,000 seenM1
- £1.40 per loaf caoA1
- Answer: £1.40 per loaf.
Question 12
- change = 450 - 400 = 50 seenM1
- 50 / 400 x 100 seenM1
- 12.5% caoA1
- Answer: 12.5% increase.
Question 13
- identifies that labour productivity increased (400 to 450) or gives the figuresB1
- identifies that unit cost decreased (£1.50 to £1.40) or gives the figuresB1
- identifies that capacity utilisation increased (80% to 90%) or gives the figuresB1
- explains the link between increased output per worker and improved efficiency, reducing unit costB1
- explains how higher capacity utilisation reduces the cost of spare capacity and spreads fixed costsB1
- considers a limitation or caveat, for example increased absolute costs, one-off effects, or quality/overtime concernsB1
Question 14
- Level 1 Makes simple statements about problems or recommendations with little use of the pack figures and limited linked explanation.1-3
- Level 2 Provides developed points using some pack figures, analyses one or two problems and gives plausible recommendations, but the judgement is not fully supported.4-6
- Level 3 Weighs several operational problems and evaluates recommended actions, uses specific pack figures (productivity, unit cost, capacity utilisation) to support the assessment, and reaches a justified conclusion.7-9
- Indicative content:
- Problems to consider: even though productivity rose, total costs increased from £36,000 to £37,800, so managers must check whether cost rises are due to overtime, higher material costs, or one-off payments and whether these threaten margins.
- High capacity utilisation at 90% reduces spare capacity but may leave little room for maintenance or demand spikes, increasing risk of breakdowns which could force costly disruption.
- If the same number of workers produced more output in Period 2, consider staff workload and morale: sustained higher output per worker might lead to fatigue, mistakes or reduced quality unless supported by training or investment.
- Recommendations: monitor and control variable costs and overtime to ensure unit-cost improvements are sustainable; analyse the rise in total costs to locate avoidable increases.
- Recommendations: consider small capacity expansion or flexible shifts to avoid running consistently at 90% which risks disruption, or schedule regular maintenance windows to reduce breakdown risk.
- Use of figures: reference the rise in productivity from 400 to 450 and unit cost fall from £1.50 to £1.40 as evidence of improved efficiency, but balance this against total cost rise of £1,800 and the move from 80% to 90% utilisation.
- Judgement: a justified conclusion might argue that overall performance improved and the business should try to sustain gains, but managers must address rising absolute costs and the risks of high utilisation by improving cost control and introducing capacity-flexibility measures.
Mark your answers