Quality Management: Total Quality Management and Cost of Quality

Quality is the extent to which a product or service meets customer expectations and specifications, consistently and without defects. Total Quality Management (TQM) is a philosophy in which every employee, not only a separate quality-control department, takes responsibility for quality at every stage of the process, aiming to prevent defects before they happen rather than catch them afterwards. The cost of quality has four parts: prevention costs, spent stopping defects occurring (staff training, better equipment); appraisal costs, spent checking for defects (inspection, testing); internal failure costs, incurred when a defect is caught before the product reaches the customer (scrapped or reworked output); and external failure costs, incurred when a defect reaches the customer (returns, refunds, warranty claims and reputational damage). TQM aims to shift spending towards prevention, since prevention costs are far smaller than the external failure costs a defect can cause once it reaches a customer.

Year 12-13 (A Level)Managing business activitiesAQAWJECEduqas

Before you start

Make sure you're comfortable with these topics first:

Method

  1. Define quality as meeting customer expectations consistently, then distinguish TQM (a whole-business culture where every employee owns quality) from older quality control, where a separate inspection team checks output after it is made and defects are found late.
  2. Learn the four categories of the cost of quality and place a given cost into the correct category: prevention (before production, e.g. staff training), appraisal (during production, e.g. inspection), internal failure (defect caught in-house, e.g. reworking), external failure (defect reaches the customer, e.g. refunds, brand damage).
  3. Learn the central argument for TQM: spending more on prevention reduces appraisal, internal failure and, most importantly, external failure costs, since a defect is cheapest to fix the earlier it is caught, and external failure additionally risks losing future customers, which is not fully captured in the direct refund cost alone.
  4. When a case gives cost-of-quality figures, calculate the total cost of quality by summing the four categories, and compare the balance between them (e.g. a high external failure cost relative to prevention spend signals a reactive rather than a preventive approach).
  5. Link quality to competitive advantage: strong, consistent quality can support premium pricing, brand reputation and customer loyalty, while poor quality can undermine a differentiation strategy even if the underlying product design is strong.
  6. For an evaluate question, weigh the upfront cost and disruption of introducing TQM (training time, culture change, possible short-term output loss) against the longer-term saving in failure costs and the strategic benefit of an improved reputation.

Worked example

A manufacturer's cost of quality report shows: prevention costs 8,000 pounds, appraisal costs 15,000 pounds, internal failure costs 22,000 pounds, external failure costs 55,000 pounds. Calculate the total cost of quality, and use the figures to explain why the business should consider adopting TQM.

  1. Calculate the total cost of quality: sum all four categories, 8,000 + 15,000 + 22,000 + 55,000 = 100,000 pounds.
  2. Calculate what share of the total is external failure: 55,000 / 100,000 x 100 = 55%.
  3. Compare prevention spend to external failure spend: prevention is only 8,000 pounds, compared with 55,000 pounds spent on external failure, a ratio of roughly 1:7.
  4. Interpret the imbalance: more than half of all quality-related cost is being spent after a defect has already reached the customer, which is the most expensive and most reputationally damaging stage to catch a problem.
  5. Conclude: adopting TQM would raise prevention spending (training, better process design), which should reduce both internal and external failure costs by a larger amount than the extra prevention spend, cutting the 100,000-pound total cost of quality overall.

Practice questions

Type your answer and press Check to be marked straight away, or reveal the answer and mark yourself.

Q1Define Total Quality Management (TQM).Show answer

Answer: A business-wide philosophy in which every employee, at every stage of the process, takes responsibility for preventing defects and meeting quality standards, rather than quality being checked only by a separate inspection team.

Got it right?
Q2State which category of the cost of quality staff training on defect prevention falls into.Show answer

Answer: Prevention cost.

Got it right?
Q3State which category of the cost of quality a customer refund for a faulty product falls into.Show answer

Answer: External failure cost.

Got it right?
Q4Give one example of an internal failure cost.Show answer

Answer: The cost of reworking or scrapping a defective product that is caught before it reaches the customer, for example, the cost of the wasted materials and labour.

Got it right?
Q5A business has prevention costs of 5,000 pounds, appraisal costs of 9,000 pounds, internal failure costs of 6,000 pounds and external failure costs of 40,000 pounds. Calculate the total cost of quality.Show answer

Answer: 5,000 + 9,000 + 6,000 + 40,000 = 60,000 pounds.

Got it right?
Q6Explain why external failure costs are usually considered the most damaging category of the cost of quality.Show answer

Answer: Because they occur after a faulty product has already reached the customer, so on top of direct costs like refunds and returns, they can damage the business's reputation and cause the loss of future repeat custom, which is much harder to recover from than an in-house defect.

Got it right?
Q7State one way a business can reduce its appraisal costs without increasing its risk of undetected defects.Show answer

Answer: By investing more in prevention (e.g. better staff training or equipment) so fewer defects occur in the first place, reducing the amount of inspection and testing needed.

Got it right?

Exam-style questions

Written in the style of a A Level Business exam paper, with a full mark scheme.

Q1[6 marks]

Explain two reasons why a business might introduce Total Quality Management (TQM).

Show mark scheme

Tick each line you got. Your score builds from the marks on the scheme.

Nothing ticked yet - 6 available

Got it right?
Q2[12 marks]

A kitchenware manufacturer's cost of quality report shows: prevention 10,000 pounds, appraisal 20,000 pounds, internal failure 18,000 pounds, external failure 72,000 pounds, a total of 120,000 pounds. The operations director proposes investing 25,000 pounds a year in TQM training and process redesign, forecasting this will cut internal failure costs by 40% and external failure costs by 60%, while appraisal costs stay roughly the same. Analyse the likely financial impact of the operations director's proposal.

Show mark scheme

Tick each line you got. Your score builds from the marks on the scheme.

Nothing ticked yet - 12 available

Got it right?

See real A Level Business past-paper questions, with official mark schemes

Free printable worksheet

Want more practice on paper? Download the quality management: total quality management and cost of quality worksheet pack - 6 pages of exam-style questions with a full mark scheme. One email opens every download in this browser for 14 days - no account, no card. Print it for personal and classroom use.

Next topics

Ready to practise quality management: total quality management and cost of quality? Add it to a printable topic pack for this student in the Pack Builder.

Add to my pack

Not quite what you needed?

Tell us what is missing on quality management: total quality management and cost of quality, or which topic to write up next. Every request is read, and we reply to every one.

Build a full practice pack.

This topic is one of hundreds in the library - pick the ones a student needs and generate a printable PDF in minutes.