Worked question 4 - Energy Resources and Electricity Generation
Answer and mark scheme
Question 4
| Credit | Answer or working |
|---|---|
| B1 | B meets the construction budget: 45 is within 60, whereas A needs 80 |
| B1 | A has lower annual operating costs: 3 cost units per year compared with 9 for B; accept B costs 6 more cost units per year |
- Answer: B meets the construction budget because 45 ≤ 60, while A requires 80. A has lower annual operating costs: 3 cost units per year compared with 9 for B.