Quality Management: Total Quality Management and Cost of Quality - Worksheets, Questions and Revision
10 original exam-style questions - 3 pages of questions with a full mark scheme - free printable PDF.
Quality Management: Total Quality Management and Cost of Quality revision guideWrite-in editionMore A Level Business practice
This topic is chapter 1 of A Level Business Topic Workbook 2.
2.6 Quality Management: Total Quality Management and Cost of Quality
- A) TQM is only about inspection of finished goods
- B) TQM focuses on preventing defects and continuous improvement across the whole business
- C) Basic checking uses employee suggestions while TQM does not
- D) TQM ignores customer feedback
Question 1
- a named external failure cost, e.g. customer refunds and replacements, warranty repairs, or compensationB1
- Answer: Customer refunds and replacements for faulty goods.
Question 2
- B caoB1
- Answer: B
Question 3
- identifies that quality circles involve employees meeting to identify and solve quality problemsB1
- applies to BrightBrew by referring to the 1,200 internal faults and the 300 customer returnsB1
- explains how staff suggestions could change processes or machine settings to reduce internal faults, reducing the 1,200 figureB1
- explains how reducing internal faults is likely to reduce customer returns and the £4,500 external failure costB1
- explains how fewer faults could lower inspection and rework time, improving efficiency and possibly reducing appraisal costs long termB1
- offers a justified outcome for BrightBrew, e.g. lower total monthly quality costs and higher customer satisfactionB1
- Answer: Quality circles bring together operators and supervisors to spot causes of the 1,200 internal faults and the 300 returns. Staff can propose changes to production routines or machine settings that cut internal rejects, which will reduce the number of customer returns and the £4,500 monthly external failure cost. Fewer faults also reduce time spent on inspection and rework, improving efficiency and potentially lowering ongoing appraisal costs. Overall BrightBrew would expect lower total monthly quality costs and improved customer satisfaction.
Question 4
- a named appraisal cost, e.g. inspection equipment, final product inspection, or quality auditsB1
- Answer: Inspection equipment or final product inspection.
Question 5
- 1,200 / 50,000 seenM1
- 2.4% caoA1
- Answer: 2.4%.
Question 6
- 300 / 50,000 seenM1
- 0.6% caoA1
- Answer: 0.6%.
Question 7
- 1,500 + 2,000 + 4,500 seenM1
- £8,000 caoA1
- Answer: £8,000 per month.
Question 8
- identifies effect on customer satisfaction, e.g. fewer returns, happier customersB1
- develops the point on costs, e.g. fewer defects reduce rework and external failure costsB1
- links both effects, e.g. satisfied customers lead to repeat sales while lower failure costs improve marginsB1
- Answer: Higher quality leads to fewer returns and defects, increasing customer satisfaction and loyalty; at the same time fewer defects reduce rework and external failure costs, improving cost efficiency and profit margins.
Question 9
- identifies relevant facts from the data, e.g. there are many more internal faults (1,200) than returns (300), and external failure costs are large (£4,500)B1
- explains that internal faults indicate production problems that, if fixed, can reduce both appraisal and external failure costsB1
- explains that external returns cost BrightBrew directly £4,500 and risk harming reputation, so reducing returns has high priorityB1
- applies cost figures to argue where marginal gains are larger, e.g. cutting returns saves external failure costs directly whereas reducing internal faults can also lower inspection/reworkB1
- analyses trade-offs, e.g. investing more in training or process changes (prevention) may increase prevention costs but reduce larger external failure costs over timeB1
- analyses short-term vs long-term priorities, e.g. quick wins might be improved inspection or targeted fixes to reduce immediate returns, while TQM style prevention is a longer term investmentB1
- considers capacity and cost-effectiveness, e.g. given training is 1,500 and inspection 2,000, reallocating some of that to prevention actions could be justified if it reduces the 4,500 external costB1
- draws a reasoned conclusion about priorities, e.g. focus first on causes of returns while planning prevention measures to reduce internal faults and long-term external costsB1
- Answer: The data show many more internal faults (1,200) than customer returns (300), but external failure costs are high at £4,500 per month. This suggests BrightBrew should prioritise actions that reduce returns because each return creates direct cost and reputational risk, giving an immediate benefit. However internal faults are the root cause and fixing them through prevention (training or process changes) can reduce both appraisal costs and external failure costs over time. Investment in prevention increases short-term prevention costs but can be justified if it reduces the larger external costs. A balanced approach is sensible: short-term targeted fixes to cut returns quickly while implementing prevention measures, such as quality circles, to reduce internal faults and lower total monthly quality costs in the longer term.
Question 10
- Level 1 Makes simple, undeveloped comments about TQM and BrightBrew, with little or no use of the pack's figures and no clear recommendation.1-3
- Level 2 Gives a developed argument for or against introducing TQM, using some of the BrightBrew figures, but does not fully weigh both costs and benefits or reach a clearly justified recommendation.4-6
- Level 3 Weighs the evidence for and against introducing TQM using the BrightBrew figures, analyses trade-offs and longer term effects, and reaches a justified recommendation supported by that analysis.7-9
- Indicative content:
- Possible benefits: reduction in internal faults (1,200) and customer returns (300) which would lower external failure costs currently £4,500 per month and reduce rework and appraisal time, improving cost efficiency.
- Possible benefits continued: employee involvement through TQM and quality circles could yield practical low-cost fixes, improved morale and continuous improvement across production, strengthening brand and reducing volatility in quality.
- Costs and drawbacks: implementing TQM may require upfront investment in training beyond the existing £1,500, time spent in meetings and potential temporary disruption while new processes are embedded, increasing short-term prevention costs.
- Trade-offs: short-term prevention and implementation costs should be compared with likely reductions in external failure costs and improved sales from higher customer satisfaction; figures such as a potential £1,800 saving from reduced returns should be used to judge payback.
- Longer term view: TQM is strategic and reduces total cost of quality over time, but may not be the fastest way to cut an immediate spike in returns; a combined approach of short-term corrective actions and long-term TQM is often best.
- Judgement: a balanced conclusion that either recommends TQM because its long-term reductions in the £4,500 external cost and in internal failures justify the investment, or recommends a staged approach starting with targeted fixes and piloting TQM in one area before full rollout, with reasons supported by the BrightBrew figures.
Mark your answers
Check answers without an account. Some answers can be checked automatically; use the mark scheme to mark the rest.