Production processes: job, batch and flow - Worksheets, Questions and Revision

15 original exam-style questions - 5 pages of questions with a full mark scheme - free printable PDF.

Download PDFJump to mark scheme (page 6)
« Previous: Building an Integrated Marketing MixNext: Procurement and managing stock »
Revision Library
revisionlibrary.co.uk
GCSE · Business operations

BUS.OP1 Production processes: job, batch and flow

AQA 8132 · Calculator allowed · about 60 minutes
Total Marks
Name: _______________________________    Date: ____ / ____ / ______
Answer ALL questions in the spaces provided. Show your working for any calculation: method marks are available even if your final answer is wrong. Puddlecombe Furniture Co, used throughout this pack, is a fictional business.
1
Which one of the following best describes job production?
  • A) Making a single, unique product to meet one customer's specific order
  • B) Making thousands of identical products continuously on a moving line
  • C) Making a large batch of one product before switching the line over to make a different product
  • D) Buying finished products from another business to resell
(Total for Question 1 is 1 mark)
2
Which one of the following best describes flow production?
  • A) Making a single, unique product to a customer's exact specification
  • B) A continuous production process making a standardised product, often on a moving assembly line
  • C) Producing goods only when a customer places an order, with no stock held at all
  • D) Grouping orders from several customers together into one large one-off batch
(Total for Question 2 is 1 mark)
3
State two features of batch production.
(Total for Question 3 is 2 marks)
4
Puddlecombe Furniture Co makes one-off, bespoke garden benches to each customer's exact design using job production.
Explain one benefit to Puddlecombe of using job production for these bespoke benches.
(Total for Question 4 is 3 marks)
5
Puddlecombe also batch-produces standard picnic tables. Changing the line over for a new batch takes 3 hours, after which each table takes 0.5 hours to make.
Calculate the total time needed to produce a batch of 26 picnic tables. Show your working.
(Total for Question 5 is 2 marks)
6
The workshop operates for 21 hours in total on the batch. Using the 3-hour changeover time and the 0.5-hour production time per table from question 5, calculate how many tables can be completed in this 21-hour shift. Show your working.
(Total for Question 6 is 2 marks)
7
Explain one drawback to Puddlecombe of using batch production for its picnic tables.
(Total for Question 7 is 3 marks)
8
The 3-hour changeover for the picnic-table batch is carried out by a worker paid 20 pounds an hour.
(a)Calculate the changeover cost per table if the batch size is 20 tables.(2)
(b)Calculate the changeover cost per table if the batch size is instead increased to 60 tables.(2)
(Total for Question 8 is 4 marks)
9
Each picnic table also has a variable cost (materials and direct labour) of 34 pounds. Using your answer to question 8a, calculate the total cost per table at a batch size of 20. Show your working.
(Total for Question 9 is 2 marks)
10
Using your answer to question 8b, calculate the total cost per table at a batch size of 60. Show your working.
(Total for Question 10 is 2 marks)
11
Using your answers to questions 9 and 10, explain why the cost per table falls as the batch size increases.
(Total for Question 11 is 3 marks)
12
Puddlecombe also runs one flow-production line making a simple wooden plant trough, with a cycle time of 4 minutes per trough.
(a)Calculate how many troughs the line can complete in one 480-minute (8-hour) shift.(2)
(b)A final quality check rejects 5% of these troughs. Using your answer to part a, calculate how many troughs pass the quality check.(2)
(Total for Question 12 is 4 marks)
13
Explain one drawback to Puddlecombe of using flow production for the plant trough line.
(Total for Question 13 is 3 marks)
14
For one bespoke bench (job production), the customer's design needs 22 hours of skilled labour at 19 pounds an hour, plus 132 pounds of materials. Puddlecombe sells the finished bench for 850 pounds.
(a)Calculate the total cost of making this bench.(2)
(b)Using your answer to part a, calculate the profit made on this bench.(2)
(Total for Question 14 is 4 marks)
15
Puddlecombe's picnic-table line currently uses batch production: at a batch size of 60, the cost per table is 35 pounds (question 10), but changeovers between batches waste time (question 7). Puddlecombe is considering converting this line to flow production instead, similar to its plant-trough line, which completes 120 units per 8-hour shift with a 5% rejection rate (question 12) but needed a large amount of capital to set up and cannot easily be changed to a different design (question 13).
Recommend whether Puddlecombe should convert its picnic-table line from batch to flow production. Justify your answer using the figures and points made earlier in this pack.
(Total for Question 15 is 9 marks)
Mark scheme · BUS.OP1 Production processes: job, batch and flow

Question 1

Question 2

Question 3

Question 4

Question 5

Question 6

Question 7

Question 8

Question 9

Question 10

Question 11

Question 12

Question 13

Question 14

Question 15