Greenway Cafe refurbishment project, activities, durations (days) and dependencies. Use these figures for questions 7 to 16.
Activities:
A: Design layout, duration 2 days, no predecessors
B: Remove old fittings, duration 3 days, predecessor A
C: Electrical rewiring, duration 4 days, predecessor A
D: New plumbing, duration 2 days, predecessor B
E: Decorating and painting, duration 3 days, predecessors C and D
F: Furnishing and final fit-out, duration 2 days, predecessor E
Using the table above, how many activities are listed for this project?
(Total for Question 6 is 1 mark)