Critical Path Analysis: Network Diagrams and the Critical Path - Worksheets, Questions and Revision

16 original exam-style questions - 3 pages of questions with a full mark scheme - free printable PDF.

Download PDFJump to mark scheme (page 4)
« Previous: Budgeting and Variance Analysis: Favourable and Adverse VariancesNext: Multinationals and Global Market Entry Strategies »
Revision Library
revisionlibrary.co.uk
A-Level · Operations and Project Planning

BUS.AL14 Critical Path Analysis: Network Diagrams and the Critical Path

AQA 7132 · Calculator allowed · about 60 minutes
Total Marks
Name: _______________________________    Date: ____ / ____ / ______
Answer ALL questions in the spaces provided. Show working for every calculation. The project details needed for questions 6 to 16 are given in question 6's prompt and repeated where necessary.
1
Which one of the following best describes the critical path in a project network diagram?
  • A) The path with the greatest number of activities
  • B) The sequence of activities that has the longest total duration and zero float
  • C) The path that finishes first
  • D) The sequence of activities with the smallest durations
(Total for Question 1 is 1 mark)
2
State the meaning of 'float' (also called slack) for an activity in a network diagram.
(Total for Question 2 is 1 mark)
3
Identify one benefit of using critical path analysis (CPA) for project planning in a small business.
(Total for Question 3 is 1 mark)
4
State two limitations of critical path analysis as a planning tool.
(Total for Question 4 is 2 marks)
5
Name the two passes used in critical path calculation and state briefly what each pass finds.
(Total for Question 5 is 2 marks)
6
Greenway Cafe refurbishment project, activities, durations (days) and dependencies. Use these figures for questions 7 to 16.
Activities:
A: Design layout, duration 2 days, no predecessors
B: Remove old fittings, duration 3 days, predecessor A
C: Electrical rewiring, duration 4 days, predecessor A
D: New plumbing, duration 2 days, predecessor B
E: Decorating and painting, duration 3 days, predecessors C and D
F: Furnishing and final fit-out, duration 2 days, predecessor E
Using the table above, how many activities are listed for this project?
(Total for Question 6 is 1 mark)
7
Using the Greenway Cafe activity data (question 6), perform the forward pass to calculate each activity's earliest start (ES) and earliest finish (EF) times. Show your working and give ES and EF for A, B and C.
(Total for Question 7 is 3 marks)
8
Continuing the forward pass for Greenway Cafe, give ES and EF for activities D, E and F and show brief working.
(Total for Question 8 is 3 marks)
9
Perform a backward pass using the project finish time found from the forward pass. Calculate the latest finish (LF) and latest start (LS) times for activities A, B and C. Show your working.
(Total for Question 9 is 3 marks)
10
Using your ES/EF and LS/LF values, calculate the float for activity C. Show your working and give the float in days.
(Total for Question 10 is 2 marks)
11
Identify the critical path for the Greenway Cafe project using the calculations above.
(Total for Question 11 is 1 mark)
12
What is the minimum project completion time for the Greenway Cafe refurbishment, in days, as found from the forward pass?
(Total for Question 12 is 1 mark)
13
Which activity has a float of 1 day? Answer using the activity letter and justify in one short sentence referring to ES and LS or EF and LF.
(Total for Question 13 is 3 marks)
14
Explain one operational benefit to Greenway Cafe of identifying the critical path for this refurbishment project. Use the project context in your answer.
(Total for Question 14 is 3 marks)
15
Explain one limitation of critical path analysis for Greenway Cafe's refurbishment project. Use the project context in your answer.
(Total for Question 15 is 3 marks)
16
Evaluate the usefulness of critical path analysis for planning Greenway Cafe's refurbishment project. In your answer, consider benefits and limitations and reach a justified judgement that refers to the project data given in this pack.
(Total for Question 16 is 9 marks)
Mark scheme · BUS.AL14 Critical Path Analysis: Network Diagrams and the Critical Path

Question 1

Question 2

Question 3

Question 4

Question 5

Question 6

Question 7

Question 8

Question 9

Question 10

Question 11

Question 12

Question 13

Question 14

Question 15

Question 16