Critical Path Analysis: Network Diagrams and the Critical Path - Worksheets, Questions and Revision
16 original exam-style questions - 4 pages of questions with a full mark scheme - free printable PDF.
Critical Path Analysis: Network Diagrams and the Critical Path revision guideWrite-in editionMore A Level Business practice
This topic is chapter 8 of A Level Business Topic Workbook 1 and chapter 8 of A Level Business 10-Minute Tests.
2.2 Critical Path Analysis: Network Diagrams and the Critical Path
- A) The path with the greatest number of activities
- B) The sequence of activities that has the longest total duration and zero float
- C) The path that finishes first
- D) The sequence of activities with the smallest durations
Activities:
A: Design layout, duration 2 days, no predecessors
B: Remove old fittings, duration 3 days, predecessor A
C: Electrical rewiring, duration 4 days, predecessor A
D: New plumbing, duration 2 days, predecessor B
E: Decorating and painting, duration 3 days, predecessors C and D
F: Furnishing and final fit-out, duration 2 days, predecessor E
Using the table above, how many activities are listed for this project?
Question 1
- B caoB1
- Answer: B
Question 2
- float is the amount of time an activity can be delayed without delaying the project completionB1
- Answer: Float is the amount of time an activity can be delayed without delaying the project completion date.
Question 3
- identifies a correct benefit, e.g. shows the shortest possible completion time or helps prioritise resourcesB1
- Answer: Shows the shortest possible project completion time and helps prioritise resources for critical activities.
Question 4
- 6 caoB1
- Answer: 6 activities.
Question 5
- it requires accurate duration estimates which may be hard to predictB1
- it ignores some qualitative risks and resource conflicts unless these are modelled separatelyB1
- Answer: It needs accurate duration estimates which may be hard to predict; it can ignore qualitative risks and resource conflicts unless modelled separately.
Question 6
- forward pass, which finds earliest start and earliest finish timesB1
- backward pass, which finds latest finish and latest start timesB1
- Answer: Forward pass finds earliest start and earliest finish times; backward pass finds latest finish and latest start times.
Question 7
- A-B-D-E-F caoB1
- Answer: A - B - D - E - F.
Question 8
- 12 days caoB1
- Answer: 12 days.
Question 9
- identifies a benefit, e.g. helps the owner to prioritise resources on critical activitiesB1
- develops the point in context, e.g. ensures workers and materials are scheduled for A, B, D, E and F firstB1
- links to an outcome, e.g. reducing the risk of delaying the cafe opening and losing tradeB1
- Answer: It helps the owner to prioritise resources on critical activities: by scheduling workers and materials first for A, B, D, E and F the cafe reduces the risk of delaying the opening and losing trade.
Question 10
- correct method for forward pass stated or used: ES of start activity = 0 and for successors ES = max(EF of predecessors)M1
- ES and EF correctly calculated for A and B or evidence of correct substitution, e.g. A ES 0 EF 2; B ES 2 EF 5M1
- C ES 2 EF 6 caoA1
- Answer: A: ES 0, EF 2. B: ES 2, EF 5. C: ES 2, EF 6.
Question 11
- method applied: ES of an activity is the maximum EF of its predecessorsM1
- correct ES and EF for D and E seen or implied, e.g. D ES 5 EF 7; E ES 7 EF 10M1
- F ES 10 EF 12 caoA1
- Answer: D: ES 5, EF 7. E: ES 7, EF 10. F: ES 10, EF 12.
Question 12
- correct method for float, e.g. float = LS - ES or float = LF - EFM1
- 1 day caoA1
- Answer: Float for C = LS - ES = 3 - 2 = 1 day.
Question 13
- identifies activity CB1
- shows the calculation, e.g. LS - ES = 3 - 2B1
- gives the float as 1 dayB1
- Answer: Activity C. LS 3 minus ES 2 = 1 day float, so C has 1 day float.
Question 14
- identifies a limitation, e.g. durations may be uncertain or underestimatedB1
- develops the point in context, e.g. if electrical work takes longer than 4 days or a supplier delay occurs the plan becomes inaccurateB1
- links to an outcome, e.g. this could cause the project to overrun despite the CPA planB1
- Answer: Durations may be uncertain: if the electrical rewiring or material deliveries take longer than estimated the CPA schedule becomes inaccurate and the project could overrun despite the plan.
Question 15
- sets project finish as EF of final activity, 12 days, and states backward pass method: for an activity LF = min(LS of successors)M1
- correct LF and LS for B and C seen or implied, e.g. B LF 5 LS 2; C LF 7 LS 3M1
- A LF 2 LS 0 caoA1
- Answer: A: LF 2, LS 0. B: LF 5, LS 2. C: LF 7, LS 3.
Question 16
- Level 1 Makes simple, undeveloped statements about CPA, such as naming a benefit or limitation, with little or no reference to the project data and no clear judgement.1-3
- Level 2 Provides developed points about CPA, using some project figures (for example the 12 day duration or the identification of the critical path A-B-D-E-F), but analysis is not balanced or the conclusion is not fully justified.4-6
- Level 3 Weighs benefits and limitations with clear use of the project data, shows how CPA helps reduce completion time and allocate resources to A-B-D-E-F, but also considers issues such as uncertainty in duration estimates and resource conflicts, and reaches a justified and balanced judgement.7-9
- Indicative content:
- Benefits: CPA shows the minimum completion time is 12 days and identifies the critical activities A-B-D-E-F, allowing the cafe to schedule labour and deliveries for those activities to avoid delays.
- Benefits: knowing floats, for example C has 1 day float, lets managers be flexible with less-critical tasks and protect the critical path.
- Limitations: CPA assumes the given durations are accurate; if electrical rewiring actually takes 6 days rather than 4, or if plumbing is delayed, the critical path and project finish date change and the plan is undermined.
- Limitations: CPA does not automatically resolve resource conflicts, for example if the same specialist is needed for electrical and furnishing, the schedule must be adjusted and CPA alone may not indicate the best resolution.
- Judgement: a balanced view could argue CPA is highly useful as a starting point for the Greenway Cafe project because it gives a clear minimum timescale and shows where to focus resources, but the cafe should combine CPA with contingency planning, monitoring and flexible scheduling to allow for uncertainty in durations and resource availability.