Worked question 6 - A Level Paper 2: The Global Economy
A government spends 4.5 billion pounds building a new rail line, which is expected to raise the country's potential output by 0.15% once complete, in an economy with a current potential output of 2600 billion pounds.
Calculate the expected increase in potential output resulting from this project, and comment on whether this appears to represent good value for the government's spending.
Answer
Expected increase in potential output = 2600 x 0.0015 = 3.9 billion pounds; this is smaller than the 4.5 billion pound cost in a single year, but because this rise in potential output recurs every year once the line is built, the project could still represent good value when judged over its full lifetime rather than one year alone.
Mark scheme
| M1 | for increase in potential output = potential output x 0.15% |
| M1 | for substituting 2600 x 0.0015 |
| A1 | for increase in potential output = 3.9 billion pounds |
| 1 mark for comparing this to the 4.5 billion pound cost, noting the single-year output increase (3.9 billion) is smaller than the one-off cost | |
| 1 mark for a developed point that this rise in potential output recurs every year once the line is built, so the project's value should be judged over its full lifetime rather than a single year |